Documents:
27/25 Notification28/11/2025 EN
Court Diary:
13/04/2026
Deadline for written observations from Governments and relevant institutions (cf. Article 20 of the Statute): Monday, 13 April 2026
24/04/2026
Service of the reply on the EFTA Surveillance Authority. Deadline for the rejoinder: Friday, 24 April 2026
About this case:
An action against the EFTA Surveillance Authority was brought before the EFTA Court on 24 November 2025 by Masserud Utvikling AS.
28/11/2025
Service of the Application on the EFTA Surveillance Authority. Deadline for the defence: Wednesday, 28 January 2026
13/02/2026
Service of the defence on Masserud Utvikling AS. Deadline for the Reply: Friday, 13 March 2026
13/02/2026
Deadline for written observations from Governments and relevant institutions (cf. Article 20 of the Statute): Monday, 13 April 2026
23/02/2026
Request for an extension of the time-limit to submit the reply received from Masserud Utvikling AS
24/02/2026
Service of the response to the request for the extension of the time-limit to submit the reply. New Deadline for the reply: Monday, 23 March 2026
23/03/2026
Reply received from Masserud Utvikling AS
24/03/2026
Service of the reply on the EFTA Surveillance Authority. Deadline for the rejoinder: Friday, 24 April 2026